SpaceX Starmind: FCC conditional authority for up to 1 million satellites

Thomas Rebaud
Thomas Rebaud, CEO @akka.app
November 26, 2026
•
8 min read
Follow Thomas

On 25 November 2026 the US Federal Communications Commission granted SpaceX conditional authority for Starmind, a proposed system of up to 1 million satellites that would run AI computing in orbit. That is permission for a plan, not proof it works. The authorization is not evidence that any Starmind satellite has been deployed.

Key takeaways

  • The FCC conditionally authorised up to 1 million Starmind satellites on 25 November 2026.
  • The number is a ceiling with deadlines attached, not a fleet already in orbit.
  • The system faces technical and cost challenges.

What the FCC approved on 25 November 2026

The order, numbered DA 26-1273, gives SpaceX conditional authority for its proposed Starmind orbital data-centre system of up to 1 million satellites. The regulator set out the limits itself: the satellites may operate in shells from 500 km to 1,002 km, not the 2,000 km upper limit SpaceX had asked for.

A Starlink satellite train crosses the early morning sky with birds flying nearby.
Photo by Forest Katsch on Unsplash

The licence comes with a timetable. SpaceX must deploy and operate one Starmind satellite by 25 November 2033, 10% of the authorised maximum by 25 November 2035, 50% by 25 November 2038, and the rest needed to complete the authorised constellation by 25 November 2040. The FCC set this schedule instead of using its standard milestone rules. Miss the milestones and the authorisation becomes null and void.

Two things were not settled. The FCC found the debris-mitigation plan compliant only for satellites operating below 600 km. Above that, SpaceX must file a licence-modification application with a final debris plan. The regulator also deferred SpaceX's request to use alternative disposal orbits instead of burning some satellites up in the atmosphere.

Question What is known
How many satellites are authorised? Up to 1,000,000, conditionally
At what altitudes? 500 km to 1,002 km
First satellite deadline? 25 November 2033
Full constellation deadline? 25 November 2040
Have any launched? The authorization is not evidence that any have been deployed.

How a data centre in space would work

It isn't one building floating above your head. It's many satellites, each carrying computing hardware, working as one network.

A Falcon 9 launch leaves an exhaust trail at sunset.
Photo by Tom Strecker on Unsplash

SpaceX describes Starmind as onboard AI computing powered by solar energy in sun-synchronous orbit, an orbit that keeps the satellite in a steady relationship with the sun. High-speed optical links, which use lasers, would connect the satellites and send results to Earth through Starlink. The company says heat radiates into space and that the design avoids the cooling equipment used by data centres on the ground.

The FCC order treats optical links as the main communications method. It permits Ka-band, a radio frequency range, only to monitor, locate and control satellites if the optical links fail. These backup transmissions may use 18.8–19.3 GHz space-to-Earth and 28.6–29.1 GHz Earth-to-space. They are limited to emergencies, and SpaceX must stop them if they cause harmful interference.

On the hardware, SpaceX said in August 2026 that it is partnering with NVIDIA on the AI1 compute payload, which it described as including NVIDIA Rubin GPUs and Vera CPUs. SpaceX's published AI1 specifications list compute-payload power of up to 250 kW peak and 175 kW average, with a 75 m wingspan and 30 m deployed height.

Why cooling is the hard part

Space is cold, so cooling should be easy. It isn't. In a vacuum there is no air and no water to carry heat away. Heat moves through the spacecraft and then has to leave as infrared radiation. NASA describes how much heat a radiator can reject as depending on its area, how efficiently it emits heat and the temperature gap with deep space.

That creates a hard limit. More electrical power means more waste heat, which means more radiator area. Deployable radiators then run into limits of surface area, volume, mass and integration.

Radiation is the second problem. It can cause slow, cumulative damage and sudden single-event failures. Engineers use tougher components, error correction, duplicate systems and selective power use. This adds extra equipment and power needs. Sunlight and eclipse alternate every orbit, stressing materials, and tiny debris particles can still cause serious damage at hypervelocity. Radiation-hardened processors trade performance for predictability, while commercial chips are faster and cheaper but more fragile.

Can SpaceX build and launch them fast enough?

In its May 2026 roadshow, SpaceX treated 100 metric tons to low Earth orbit per Starship V3 launch as an expected, theoretical payload capacity, and showed AI-compute-satellite deployment beginning in 2028 at 100 kW of compute per metric ton. Those were company targets, not a demonstrated capability. The FCC filing envelope caps a Starmind satellite at under 4,000 kg, without fixing a final spacecraft mass or how many would fit per launch.

Launch rate is the other bottleneck. As of 26 November 2026, Reuters reported a Starship goal of weekly flights in the first half of 2027 and twice-weekly in the second half. SpaceX's own prospectus warned that reaching enough launches, reuse and payload capacity remained uncertain, and was necessary for orbital AI compute at scale.

For context on who pays for AI hardware on the ground, see our guide to the best AI tools for small business.

Does the money work?

Two independent models say orbital computing costs more today. SemiAnalysis published a 2026 estimate putting the levelized cost of a B300 GPU at $10.91 per GPU-hour in orbit against $2.49 on Earth, counting launch, space-specific capital, ground-control and communications costs, a five-year orbital facility life, radiation-related availability loss and 20% spare-GPU redundancy for failures that can't be fixed in orbit.

Boston Consulting Group's 2026 twenty-year model estimates $660 million to $750 million per MW for orbital data centres against $230 million to $300 million per MW on the ground, a modelled 2.5 to 3 times premium.

What happens next

A first Starmind launch in the third quarter of 2027 has been described as Elon Musk's expectation. That is a reported target, not an FCC deadline and not a completed launch. The first deployment milestone is in November 2033.

SpaceX told the FCC that Starmind satellites would use engines to raise, maintain and leave orbit, with manoeuvres to avoid close approaches. It also described testing at lower altitudes before raising satellites to their operating orbits. For satellites ending their missions below 2,000 km, the FCC disposal rule calls for atmospheric reentry as soon as practicable and no later than five years after mission end. SpaceX must file status reports with the FCC every six months, due 1 January and 1 July, covering deployments, close approaches, collision-avoidance actions, satellites removed or reentered, and use of the backup Ka-band links.

The headline number is a ceiling. The evidence will come from hardware in orbit.

Frequently asked questions

What is SpaceX Starmind?

Starmind is SpaceX's proposed orbital data-centre system. The company describes it as onboard AI computing powered by solar energy in sun-synchronous orbit, with optical links between satellites and results sent to Earth through Starlink. On 25 November 2026 the FCC conditionally authorised up to 1 million of these satellites. The authorization is not evidence that any have been deployed.

Does the FCC approval mean 1 million satellites will fly?

No. One million is a ceiling, not an order to launch that many. But keeping the authorisation means meeting the milestones, which end with completing the authorised constellation by 25 November 2040. If SpaceX misses a required milestone, the authorisation becomes null and void.

What chips would these satellites use?

SpaceX has publicly identified NVIDIA Rubin GPUs and Vera CPUs for its AI1 payload. NVIDIA said separately that the first-generation Starmind satellite is planned around an optimised Vera Rubin NVL72 system. SpaceX's published specifications do not state a solar-generation rating or an energy-storage capacity.

How big is SpaceX's business today?

For the quarter ended 30 September 2026, SpaceX reported revenue of $14.575 billion and net income of $4.404 billion. Within that, the Connectivity segment brought in $5.248 billion, the Super Intelligence segment $7.560 billion and the Space segment $1.767 billion.

Bar chart showing Super Intelligence as the largest SpaceX revenue segment at $7.560 billion.
Invest in tech companies before they list
With Akka, you can invest in private tech companies from €300 per investment, with the protections professional investors get. Akka is regulated by the French AMF.
Join 4,000+ investors
Share this post
← All articles
Thomas Rebaud
Thomas Rebaud
Founder and CEO of Akka
|
Founder of Meero.com (unicorn)

You might also like

Deepen your knowledge with more articles and inspiration.

Breakthrough tech
SpaceX Starmind: FCC conditional authority for up to 1 million satellites
The FCC has conditionally authorised SpaceX’s proposed Starmind constellation of up to 1 million AI-computing satellites. Here is what the approval permits, and the technical and cost hurdles ahead.
Thomas Rebaud
Thomas Rebaud
26.11.2026
•
8 min read
AI
AI tools for small business in 2026: 7 types
Seven AI tool types for small businesses, from general assistants to automation connectors. Learn what to automate first and where human review matters.
Thomas Rebaud
Thomas Rebaud
25.11.2026
•
6 min read
Neobanks and fintech
Business bank accounts in Europe
Revolut Business leads this comparison of five European business accounts. Compare entry prices, eligibility checks and the difference between deposits and safeguarded funds.
Thomas Rebaud
Thomas Rebaud
25.11.2026
•
8 min read